PMP Formulas You Must Know (Fast Sheet)
- Authors

- Name
- passpmpnow
Short, compact, zero fluff. These are the formulas that actually show up.
Earned Value (EVM)
- PV = Planned Value
- EV = Earned Value
- AC = Actual Cost
Variances
- CV = EV - AC
- SV = EV - PV
Indexes
- CPI = EV / AC
- SPI = EV / PV
CPI < 1 → over budget
SPI < 1 → behind schedule
Forecast
- EAC = BAC / CPI (most commonly tested)
Critical Path
- Longest path = shortest possible project duration
Float = LS - ES = LF - EF
Communication Channels
channels = n(n-1)/2
This shows up every year.
Expected Monetary Value (EMV)
EMV = probability × impact
- positive → opportunity
- negative → threat