Quick Definition

TermPurpose
Change LogTracks all approved and rejected change requests
Issue LogRecords problems or concerns that need resolution

Common Exam Trap

A stakeholder complains about new requirements not being delivered — what should the PM do?

✅ Record it as an issue, not a change request (yet).
If analysis shows scope change → then raise a CR.


Flow in PMP Terms

  1. Issue detected → logged in Issue Log
  2. Analysis shows change needed → submit Change Request
  3. If approved → update Change Log